Insulation Installation Collaboration

If you've been by the space lately, it might feel a little warmer and brighter than it typically feels in winter. That is thanks to around 30 4x8 foot insulation panels that SSD members and guests installed on the ceiling during the first week of December.

Over 80 person-hours went into the project. Four meetups were scheduled in late November for Nov 29, Dec 1, Dec 2, and Dec 3, where groups of 3-6 people dedicated a few hours of their afternoon/evening to paint, cut-to-size, and/or harness the tiles between the ceiling trusses with wire.

Continue reading